| Answer:
From time to time I get that request
from customers. I am always
willing to work with someone to help
them save a few bucks, but I think in
this instance you are better off
letting the contractor provide the
materials.
On a
bid job such as yours the profit on
materials for a contractor is
low. If the contractor wants
that job he/she will try and get the
lowest prices possible on materials
from his or her suppliers.
Marking up the materials will raise
the bid price. As part of the bid the
contractor will need to cover the cost for
picking up the materials and
delivering them to the job site. This
is something that you can offer to do
for the contractor which will save him
or her time. The order can be called in
to the supply company by the
contractor and you can go and pick the
materials up. However in some
instances a truck will be required for
larger items such as conduit. A problem with this
arrangement is that sometimes the
supply company makes a mistake and
items are omitted from the original
order. Also some items could be
out of stock. You will not know
what is missing or what could be
substituted until your electrical
contractor shows up to do the work.
Offering
to buy the materials and bring them to
the job doesn't work well for the
homeowner or for the contractor. I
can speak from my own experiences on
this matter. Each time that I
agreed to this arrangement it actually
took longer to complete the job and cost the
homeowner more money.
In a
typical situation I would have to take
the time to write a neatly written or
a typed detailed list
giving quantities, names, part numbers
and descriptions of the items that I need.
I
would also give the homeowner names, addresses
and phone numbers of a few electrical
supply companies in the area. Normally
for myself I would just jot some
abbreviated things down on a scratch
piece of paper and call in my list to
the supply company.
After
providing the list to the homeowner I
would then have to wait for him to go
pick up the materials in his spare
time. When he had gathered all
of the materials I would get a call
that everything is ready and I could
come over to do the work.
I get
over to the job site ready to complete it
as quickly as possible and find that
some key material items that were on
my list are not there. The
homeowner tells me one or more the
following (Please note that these are
all true):
"I only had time on the weekend
and the places that you told me to go are
not open then, so I went to a local
hardware store instead. This is all
that they had"
"I could not fit the bigger items
in my car."
"I didn't know what some of the
things were."
"The place that I went to doesn't
have those parts."
"I sent my wife, but she could not
lift the heavy stuff."
"The supply company that you told me to go
to would not negotiate a better price so
I went somewhere else."
"I bought less wire because I did
not think that you would need a full
roll."
"When I explained to the guy at
the supply company the work that was
going to be done he said that we didn't need
those items and gave me these
instead."
As a
result of not having all of the needed
materials initially, I had to break
away from the job and go pick up the
materials. Sometimes this
lengthened the entire project by a day
or more and screwed up my schedule.
I
also charged additional time for
material pick-up because it was now an
"Extra" since it was not
part of our original agreement.
Something
else to consider; when a contractor
does not furnish material he/she does not
offer any warranty. In other words if
an item that you furnished failed
prematurely a few weeks after the job
was completed you would have to pay for
the labor as well as the material cost
to have the problem corrected.
Top |